State power utility Elektroprivreda Crne Gore (ЕPCG) will invest a total of EUR 700 million to build new renewable energy capacities and upgrade its other power generation facilities to bring them into line with environmental standards, with the aim of reducing dependence on imports due to hydrologic conditions, local media reported following a session of the Montenegrin Chamber of Economy’s energy committee.

Three new renewables facilities will have a total installed capacity of 500 MW

Three new facilities – solar power plant Briska Gora, wind farm Gvozd, and hydropower plant Komarnica – will bring 500 MW of new installed capacity, according to Ivan Mrvaljević of EPCG.

The Gvozd wind farm, a project valued at some EUR 70 million, whose test run is expected in 2022, will have an installed capacity of 150 MW and will be able to supply electricity to about 25,000 households. Gvozd, which will be built in a joint project of EPCG and Austria’s Ivicom Holding, will be located south of the existing Krnovo wind farm.

Solar power plant Briska Gora will generate 360 GWh of electricity a year

The Briska Gora solar power plant, worth EUR 200 million, with a planned annual output of 360 GWh, will also contribute significantly to an increase in power generation from renewable sources, according to Montenegrin media. The construction of the 250 MW solar power plant is expected to begin next year.

According to earlier reports, the construction of hydropower plant Komarnica will cost an estimated EUR 237.9 million. The projected capacity of this hydropower plant is 168 MW, and its expected annual output is 231.8 GWh.

Since Montenegro is under the obligation to implement the EU’s directives on limiting harmful emissions, EPCG also plans to invest over EUR 66 million to upgrade its Pljevlja thermal power plant, while additional costs in environmental fees will be around EUR 30 million, according to Montenegrin media.

MORE:

EPS to invest EUR 4.6 billion by 2027, EUR 700 million to go into hydropower, renewables

Author: Vladimir Spasić Source: Balkan Green Energy News https://balkangreenenergynews.com/eps-to-invest-eur-4-6-billion-by-2027-eur-700-million-to-go-into-hydropower-renewables/ Public power utility Elektroprivreda Srbije (EPS) intends to invest EUR 4.6 billion from 2019 to 2027, of which EUR 1.6 billion in the modernization of existing and construction of new thermal power plants (TPPs) as well as environmental protection, EUR 1,3 billion in distribution projects, EUR 1 billion…


Romanian hydropower company spends EUR 80 mln to refurbish 350MW power plant

Romania’s state-owned hydropower company Hidroelectrica will totally refurbish its hydropower plant (CHE) Râu Mare – Retezat under a EUR 80 million project, financed from own funds. The plan’s capacity will increase to 350MW after the process, Economica.net reported. The company wants to make CHE Râu Mare – Retezat the country’s largest supplier of system services,…


Romania’s hydropower company inaugurates new 12MW power plant

State-owned Hidroelectrica, the biggest electricity producer in Romania, announced that it has commissioned a 12MW power plant at Bretea – on Strei river, in Hunedoara county (western part of Romania). This is also the first automated plant, remotely controlled – a technology that will be deployed to each of Hidroelectrica’s 200 hydropower plants in operation,…